Source: Petrobras Agency
Date: 06/01/2010 17:00
Petrobras kicked-off production at the FPSO Capixaba, in the Cachalote field, Saturday (29/05). The FPSO (Floating Production, Storage, and Offloading unit) is also connected to the Baleia Franca field, both located in the "Parque das Baleias" region, off the southern coast of Espírito Santo, in the Campos Basin.
The FPSO Capixaba is chartered to Petrobras by SBM, and previously operated in the Golfinho Field. To seize the opportunity to anticipate production at the Cachalote and Baleia Franca fields, the platform's process plant was adapted, making it feasible to install the rig in the Parque das Baleias.
The first well to produce is the 7-CHT-5HA-ESS, with an initial flow rate estimated at 22,000 barrels per day. By the end of the year, the platform is expected to be interconnected to a total of nine wells in the Cachalote and Baleia Franca fields. There will be three production and two injection wells in Cachalote, and three production wells - two of which in the pre-salt layer - and one injection well in Baleia Franca. Production is scheduled to peak in December 2010, at an expected volume of 100,000 barrels of oil per day.
FPSO Capixaba
Oil processing capacity: 100,000 barrels of oil per day
Gas production capacity: 3.2 million cubic meters per day
Water depth: 1,480 meters
Length: 345 meters
Height: 127 meters
Lodging: 96 workers
Storage capacity: 1,600,000 barrel
Gas production capacity: 3.2 million cubic meters per day
Water depth: 1,480 meters
Length: 345 meters
Height: 127 meters
Lodging: 96 workers
Storage capacity: 1,600,000 barrel